How much soil will you have to excavate for a ditch that is 5' wide, 3' deep, and 3,600' long?

Prepare for the California Pipeline Contractor C-34 License Exam. Study with practice quizzes, flashcards, and multiple choice questions with explanations. Boost your confidence and get ready for your exam!

Multiple Choice

How much soil will you have to excavate for a ditch that is 5' wide, 3' deep, and 3,600' long?

Explanation:
Calculating the volume of a rectangular ditch starts with cross-sectional area, then multiplies by the length. The cross-section area is width times depth: 5 ft × 3 ft = 15 ft². Multiply by the length of 3,600 ft to get 54,000 cubic feet. Convert to cubic yards by dividing by 27 (since 1 yd³ = 27 ft³): 54,000 ÷ 27 = 2,000 cubic yards. So the ditch requires excavating 2,000 cubic yards of soil.

Calculating the volume of a rectangular ditch starts with cross-sectional area, then multiplies by the length. The cross-section area is width times depth: 5 ft × 3 ft = 15 ft². Multiply by the length of 3,600 ft to get 54,000 cubic feet. Convert to cubic yards by dividing by 27 (since 1 yd³ = 27 ft³): 54,000 ÷ 27 = 2,000 cubic yards. So the ditch requires excavating 2,000 cubic yards of soil.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy